The following tutorial for xpdrainage is intended as an introduction to the general workflow and design elements used for sizing stormwater systems for a typical site development project. Pre- and Post-Developed catchment runoff is evaluated, as well as the effectiveness of the Post-Developed Stormwater Control Treatment Train. Upon completion of the tutorial, you are encouraged to further explore the wide variety of elements available for use within the software, such as the numerous types of Stormwater Controls (SWC) and Outfalls.

The table below provides the list of topics covered in this tutorial - click the topic to go to that Tutorial Chapter. Download the Tutorial Model in order to select the associated Phases and follow the Tutorial in xpdrainage.  

Chapter NumberTutorial ChapterModel Phase to start Chapter
1Existing SiteExisting Site
2Developed SiteDeveloped
3Layout Treatment SystemDeveloped
4ResultsSizing of Treatment
5Sizing of Treatment SystemSizing of Treatment
6TemplatesCompleted Design